KAYSERI - BOĞAZKÖPRÜ - ULUKIŞLA - YENICE, MERSIN - YENICE - ADANA - TOPRAKKALE POWER SUPPLY AND TRANSFORMER SUBSTATIONS AND SCADA SYSTEMS CONSTRUCTION
Starting Date 2012
Completion Date 2016
Line Length 427,3 Km.
Number of Substations 9 Substations 154 / 25 kV.
EXPLANATION
The sections of the Kayseri-Bağazköprü-Ulukışla-Yenice-Mersin-Yenice-Adana-Toprakkale lines are 283,7 km single track and 143,6 km double tracks and total is 427,3 km. The Project consist of six sections. The first five sections are comprising the establishment of the catenary system but, the section VI is comprising the substations, remote control (SCADA) system and building construction. Substations, Remote Control (SCADA ) System and Building Construction 9 pieces 154/25 kV substations will be established in the all lines and each substation will has two traction transformers. A remote control(SCADA) system will be erected to control, supervise and monitor the electrical equipment on the line. In this scope, installation and connection of the one control center and 52 remote terminal unit will be realized .