THE TUNNEL WORKS OF IZMIR LRS PHASE II, THE REPLENISHMENT WORKS OF IZMIR SPOR HATAY STATIONS AND THE REPLENISHMENT WORK OF IZMIR SPOR HATAY STATIONS AND THE REPLENISHMENT WORK OF IZMIR LRS PART I, PHASE III BETWEEN BORNOVA HASTANE - EVKA 3 STATIONS (SIGNA
Starting Date 2011
Completion Date 2012
Number of Stations 10
Scope Installation of Signalling Systems, Test & Commissioning
EXPLANATION
The existing İzmir LRTS consists of an 11-km line with 10 stations and a depot operated since 2000. A total of 7,4km line shall be added to the existing system in 3 different phases. The Signalling System Installation and Testing & Commissioning works of the additional lines are performed within the scope of our company. The scope of the Signalling System to be installed includes the following:
85-km Cable, 52 ea. Signals, 12 Point Machine & Local Control Panel, 190 Balises, 46 Impedance Bonds, 116 Insulated Fishplates, 232 Track Circuits, Signalling Panels, Rail Circuits, UPS Systems, System Installations, System Integrations, Testing and Commissioning works, etc.