SULTANÇIFTLIĞI EDIRNEKAPI LIGHT RAIL TRANSPORTATION PROJECT
Starting Date 2003
Completion Date 2007
Line Length 12.572 Km.
Number of Station 17
Scope Desing and Construction of Electro - Mechanical System
EXPLANATION
Sultançiftliği - Edirnekapı LTR Project had designed as double track and length of the line is 12.572 meters.
Total of 30 Km. Catenary works, which has level crossing region of 18 Km. and tunnel region of 12.7 Km., was carried out within the scope of the project.
There are 17 Stations (3 middle, 14 side peron), The line starts form Mescid-i Selam and reaches to Edirne Kapi. The line of 5 km between Karadeniz Mah. - Ali Fuat Başgil - Uluyol - Topçular Stations are underground tunnel.