Construction of Electrification Systems (Transformer Power Substation) Along the Halkalı - Cerkezkoy Line


Starting Date  : 02.01.2014

Line Length   : 87 km Single Line, 7 Stations and 105 km Catenary Line

 

The scope of the Project is the establishment of 105 km long (where the 87 km of it is single line) Halkalı-Çerkezköy catenary line. The project will be renovated along the neutral zones between the substations. For the line maintanence, 1 Catenary maintenance automobile will be procured.